Raises Many Questions About Presidio Watershed
PHRA supports the restoration of the
Tennessee Hollow Watershed in the Presidio, but needs more
information to comment on specific points of the plan.
The watershed is an area of 210 acres that
extends from the southern edge of the Presidio to the
lagoon/marsh at Crissy Field. Most of the runoff has been
diverted into culverts and concrete-lined canals.
Among the questions PHRA is asking the
Presidio Trust:
-
To "daylight"
the natural stream beds, how much fill will have to be
removed and where? What are the remediation issues involved?
We have heard that in some places the stream is 25 feet
below the surface. What would be the grading impact on
adjacent land uses and pedestrian access?
-
Three tributaries have
been identified in the watershed. Are all three stream beds
covered? What are the restoration plans for each of them?
-
How would the removal of
the MacArthur Avenue housing impact the mandate of achieving
financial self-sufficiency and how would its demolition be
staged? Will any historic housing be demolished? Are there
plans to replace the housing units? PHRA opposes the banking
and eventual replacement of demolished structures in another
location. Since the Presidio Trust Act calls for balancing
the preservation of "natural, historic, scenic,
cultural and recreational resources" and the protection
of the Presidio from development, we consider unnecessary
new construction antithetical to the Act and a threat to
this balance.
-
Would the two playing
fields that would be removed be replaced? Where and when?
-
How many trees will be
removed and, specifically, where and what kind? Where a tree
removal is proposed, what would be the effects on wind and
climate change and how will those changes affect the public’s
enjoyment of the watershed area?
-
What will be the
parameters for public access to the restored stream(s)? Will
the public be able to meander or picnic along the stream,
play in it, or jump across it?
-
What are the estimated
costs for this project?
- How would the project be staged? How would it be
integrated with the Presidio Trust Management Plan and the
Vegetation Management Plan? What are the plans for
coordinating the watershed project and the redevelopment of
Doyle Drive?
|